Question : 13 of 70
 
Marks: +1, -0

According to the information in the grid, what is the estimate at completion (EAC) for this project and what does it represent?
Budget at Completion (BAC) US $ 9,000
Earned Value (EV) US $ 1,000
Actual Cost (AC) US $ 1,500
Planned Value (PV) US $ 1,200