PMP Certification Monitoring and Controlling Test 1
© examsiri.com
Question : 13 of 70
Marks:
+1,
-0
According to the information in the grid, what is the estimate at completion (EAC) for this project and what does it represent?
| Budget at Completion (BAC) | US 9,000 |
| Earned Value (EV) | US 1,000 |
| Actual Cost (AC) | US 1,500 |
| Planned Value (PV) | US 1,200 |