PMP Certification Mix Questions Test 9

© examsiri.com
Question : 6 of 23
 
Marks: +1, -0
A project manager has been asked to lead a project. The performing organization does not have a project management office (PMO) or formal governance policies, procedures, and guidelines for this type of project.
What should the project manager do first to determine a governance approach for the project?