PMP Certification Mix Questions Test 8

© examsiri.com
Question : 62 of 70
 
Marks: +1, -0
A project in the execution phase is behind schedule and is missing some materials. The contractor submits an offer to supply the missing materials and reimburse the cost since the internal procurement process will cause more delay. The project manager does not agree with the costs submitted by the contractor for the missing materials.
What should the project manager do next?