A project manager has received an updated earned value analysis report.
The following are the key findings from the report:
Budget at completion = US$1 million
Earned value = US$0.7 million
Actual cost = US$0.75 million
Cost performance index = 0.933
Based on this information, what should the project manager conclude about project performance?