Question : 28 of 70
Marks:
+1,
-0
After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration. At this point, the project manager learns about a possible change in regulations that would prevent the product launch.
What should the project manager do to realize benefits?
What should the project manager do to realize benefits?