Question : 5 of 70
Marks:
+1,
-0
The electrical engineer has recently been promoted from lead engineer to section manager. In this new position, he will be responsible for managing projects and project resources. Over the five years he has been with the company, he was always ranked as one of the top engineers but has had no formal project management training. This is an example of what?