PMP Certification Mix Questions Test 7

© examsiri.com
Question : 34 of 70
 
Marks: +1, -0
The Project Manager is ordering cables for the video board he is developing. He can only order these cables from one company that has a patent on the design. Which of the following describes the type of procurement he is performing?