Question : 31 of 70
Marks:
+1,
-0
A project you have been managing is falling behind schedule. You have received approval to crash the project by adding an additional programmer. The cost you have negotiated is 60 US per hour. The programmer will work on the project until it is complete, then the contract will end. What type of contract is this?