PMP Certification Mix Questions Test 7

© examsiri.com
Question : 31 of 70
 
Marks: +1, -0
A project you have been managing is falling behind schedule. You have received approval to crash the project by adding an additional programmer. The cost you have negotiated is $60 US per hour. The programmer will work on the project until it is complete, then the contract will end. What type of contract is this?
Go to Question: