Activity A is worth 200, is 100% complete, and actually cost 200. Activity B is worth 75, is 90% complete, and actually cost 120 so far. Activity C is worth 200, is 75% complete, and has cost 175 so far. The total budget is 1000. What is the estimate at completion for the activities listed?