PMP Certification Mix Questions Test 6

© examsiri.com
Question : 53 of 70
 
Marks: +1, -0
You are the Project Manager of an engineering project for a cellular base station with a one-year schedule as defined by the project management plan. You need a spectrum analyzer. During the procurement process, you have decided to rent this equipment. The rental cost is $506 per month.
What type of cost is this?