You are the Project Manager of an engineering project for a cellular base station with a one-year schedule as defined by the project management plan. You need a spectrum analyzer. During the procurement process, you have decided to rent this equipment. The rental cost is 506 per month.
What type of cost is this?
What type of cost is this?