PMP Certification Mix Questions Test 6
© examsiri.com
Question : 42 of 70
Marks:
+1,
-0
You are the Project Manager on a merger and acquisition project. Activity A (3 days) and activity B (4 days) can start immediately. Activity C (2 days) can start after A and B are complete. Activity D (5 days) can begin after activity B is complete. Activity E (6 days) can begin after activity B is complete. Activity F (4 days) can begin after activities C and D are complete. Activity G (5 days) can begin after activities D and E are complete. Activity H (4 days) can begin after activities F and G are complete. What is the critical path?