PMP Certification Mix Questions Test 5

© examsiri.com
Question : 61 of 70
 
Marks: +1, -0
You are managing a moderately risky project. You have done well identifying risks and assessing them both on the probability of the risk event occurring and on the level of impact that the risk could have on your project if it actually occurred. But to help with a "next" level of qualitative risk analysis, you could use a______________