PMP Certification Mix Questions Test 5
© examsiri.com
Question : 33 of 70
Marks:
+1,
-0
A cost management plan should establish and document the various earned value rules of performance measurement. Along with defining the WBS to the level that the earned value analysis will be performed and establishing how earned value will be credited to the project (0-100, 0-50-100, and so on), which following rule is also recognized regarding performance measurement?