PMP Certification Mix Questions Test 5
© examsiri.com
Question : 10 of 70
Marks:
+1,
-0
You are working on a project to upgrade the existing fiber-optic cables in your province. You have determined that a resource can install 25 meters of cable per hour, so the duration required to install 1,000 meters would be 40 hours. This means you are using______________