Question : 50 of 70
 
Marks: +1, -0
Your project is considered very risky. You plan to perform numerous what-if scenarios on your schedule using simulation software that will define each schedule activity and calculate a range of possible durations for each activity. The simulation then will use the collected data from each activity to calculate a distribution curve (or range) for the possible outcomes of the total project.
Your planned approach is an example of which following technique?