PMP Certification Mix Questions Test 4
© examsiri.com
Question : 42 of 70
Marks:
+1,
-0
Consider the data in the table below.
Assume that your project consists only of these three activities. Your estimate at completion is 4,400.00. This means you are calculating your EAC by using which of the following formulas?
Assume that your project consists only of these three activities. Your estimate at completion is 4,400.00. This means you are calculating your EAC by using which of the following formulas?
| Activity | % Complete | PV | EV | AC |
| A | 100 | 2,000 | 2,000 | 2,200 |
| B | 50 | 1,000 | 500 | 700 |
| C | 0 | 1,000 | 0 | 0 |
Go to Question: