PMP Certification Mix Questions Test 4

© examsiri.com
Question : 42 of 70
 
Marks: +1, -0
Consider the data in the table below.
Assume that your project consists only of these three activities. Your estimate at completion is $4,400.00. This means you are calculating your EAC by using which of the following formulas?
Activity % Complete PV EV AC
A 100 2,000 2,000 2,200
B 50 1,000 500 700
C 0 1,000 0 0