Question : 44 of 70
Marks:
+1,
-0
Because you are working under a firm-fixed-price contract, management wants you to submit the final invoice and close out the contract as soon as possible.
Before final payment on the contract can be authorized, you must______________
Before final payment on the contract can be authorized, you must______________