PMP Certification Mix Questions Test 2

© examsiri.com
Question : 48 of 70
 
Marks: +1, -0
It is important on all projects to determine when and how human resources will be met. Assume that you are managing a project to assess methods for streamlining the regulatory approval process for new medical devices in your government agency. Because the agency has undergone downsizing during the past three years, subject matter experts are in short supply. You must determine whether the needed subject matter experts can be acquired from inside the agency or whether you must use contractors. This information should be documented in the______________
Go to Question: