Question : 25 of 70
Marks:
+1,
-0
Your quality assurance department recently performed a quality audit of your project and identified a number of findings and recommendations. One recommendation seems critical and should be implemented because it affects successful delivery of the product to your customer.
Your next step should be to______________
Your next step should be to______________