PMP Certification Mix Questions Test 2

© examsiri.com
Question : 16 of 70
 
Marks: +1, -0
Assume that your actual costs are $800; your planned value is $1,200; and your earned value is $1,000. Based on these data, what can be determined regarding your schedule variance?