PMP Certification Mix Questions Test 1

© examsiri.com
Question : 67 of 70
 
Marks: +1, -0
If operations on a work package were estimated to cost $1,500 and finish today but, instead, have cost $1,350 and are only two-thirds complete, the cost variance is______________
Go to Question: