PMP Certification Mix Questions Test 1
© examsiri.com
Question : 48 of 70
Marks:
+1,
-0
Review the following network diagram and table.
Number = Duration
Of the various activities, which ones would you crash and in what order?
Leeter = Activity
Number = Duration
| Time Required, Weeks Cost | Crashing Per Weeks , | ||||
| Activity | Normal | Crash | Normal | Crash | |
| A | 4 | 2 | 10,000 | 14,000 | 2,000 |
| B | 6 | 5 | 30,000 | 42,500 | 12,500 |
| C | 2 | 1 | 8,000 | 9,500 | 1,500 |
| D | 2 | 1 | 12,000 | 18,000 | 6,000 |
| E | 7 | 5 | 40,000 | 52,000 | 6,000 |
| F | 12 | 3 | 20,000 | 29,000 | 3,000 |
| G | 6 | 2 | 5,000 | 30,000 | 6,000 |
Go to Question: