Review the following network diagram and table.
Leeter = Activity
Number = Duration
Time Required, Weeks Cost $ Crashing Per Weeks , $
Activity Normal Crash Normal Crash
A 4 2 10,000 14,000 2,000
B 6 5 30,000 42,500 12,500
C 2 1 8,000 9,500 1,500
D 2 1 12,000 18,000 6,000
E 7 5 40,000 52,000 6,000
F 12 3 20,000 29,000 3,000
G 6 2 5,000 30,000 6,000
Of the various activities, which ones would you crash and in what order?