PMP Certification Mix Questions Test 1

© examsiri.com
Question : 44 of 70
 
Marks: +1, -0
Activity A has a duration of three days and begins on the morning of Monday the 4th. The successor activity, B, has a finish-to-start relationship with A. The finish-tostart relationship has three days of lag, and activity B has a duration of four days. Sunday is a non workday. Such data can help to determine______________