Question : 59 of 70
 
Marks: +1, -0
A project has been stopped during the execution phase because the construction methods are not in compliance with environmental regulations. The project manager was not aware of the environmental requirements of the project and now needs advice on how to deal with environmental compliance in future projects.
What should the project manager do to avoid a similar situation in future projects?