Question : 37 of 70
 
Marks: +1, -0
During a project's initiation, project manager A realizes that the project id dependent on and linked to other projects. Project manager A attempts to change the plans of these other projects. The other project managers feel that project manager A has overstepped boundaries.
Which document does project manager A need to revisit?