PMP Certification Executing Questions Test 6

© examsiri.com
Question : 5 of 41
 
Marks: +1, -0
During a large project's execution phase, the business owner submits an approved change that will impact different business areas. During implementation, the project manager discovers that a key stakeholder failed to be engaged with this request. This key stakeholder claims that the change will affect their business area.
What should the project manager do?