PMP Certification Executing Questions Test 6

© examsiri.com
Question : 34 of 41
 
Marks: +1, -0
An agile project manager is leading a large systems modernization project that is midway through its third iteration. Two project team members are replaced, which results in a drop in the team's productivity.
What should have been done to avoid this situation?