PMP Certification Executing Questions Test 5

© examsiri.com
Question : 67 of 70
 
Marks: +1, -0
Delays from two software vendors are causing testing times to be reduced to meet the deadline. Any impact on the delivery date is not possible, as all project resources will be reassigned to other tasks after project closing.
What should the project manager do?