Question : 44 of 70
 
Marks: +1, -0
A project manager has outsourced a critical programming task to a third party due to a lack of resources. During the implementation stage, the deliverable is behind schedule and this task must be completed before a critical deadline.
What is the first thing the project manager should do to make sure the project gets back on track?