During a demonstration of their latest deliverable for a new solution being developed, a vendor showed the client a new software module that would meet the client's needs better and improve the outcome of the project. The new software module, which was not included in the original statement of work (SOW), costs US$20,000 and would eliminate the need for US$22,000 of testing work. The client has decided that they would like to have the new module.
How should the project manager proceed?