PMP Certification Executing Questions Test 4
© examsiri.com
Question : 48 of 70
Marks:
+1,
-0
| Activity Duration | Days | Predecessor |
| A | 5 | |
| B | 2 | |
| C | 4 | A |
| D | 2 | B,C |
| E | 5 | D |
Which of the following is the correct network diagram for the table?