Question : 40 of 70
Marks:
+1,
-0
Two issues remain in the quality issue log. The first is within acceptable threshold limits, and the corrective action will be fast, increase customer satisfaction, and reduce long-term external repair costs. The second is outside performance baseline limits and will impact the project schedule.
What should the project manager do?
What should the project manager do?