PMP Certification Executing Questions Test 4

© examsiri.com
Question : 34 of 70
 
Marks: +1, -0
The team for a large software implementation project believes that the project is on track since work is being completed at a steady pace. However, based on client interactions, the project manager is concerned about meeting the project timeline.
What should the project manager do first?