Question : 3 of 70
 
Marks: +1, -0
During an IT solution implementation project, the sponsor blames the project manager for a delay in application delivery. The project manager informs the sponsor that the delay is a result of the client's failure to provide the team with the data needed to complete the task.
What should the project manager have done to avoid the sponsor's dissatisfaction?