PMP Certification Executing Questions Test 4

© examsiri.com
Question : 28 of 70
 
Marks: +1, -0
During a construction project, concrete is unable to be used because heavy rain affected its consistency. This possibility and its estimated costs were already identified in the risk register.
How should the project manager fund the additional costs?