Question : 19 of 70
 
Marks: +1, -0
After a status meeting, a project manager discovers that there are issues not being recorded properly. The reason is that project stakeholders and project team members are communicating using a new chat software tool that the project manager was unaware of.
How should the project manager respond to the use of this new chat software tool?