Question : 10 of 70
Marks:
+1,
-0
After a project was around 80% complete, the client required a change to the final product. The project team found two possible ways to make the change. One method was an easier and faster way to implement the solution, and the other was a better but more complex solution. After the team decided to use the more complex solution, they noticed that they estimated incorrectly, and it would take longer to implement the change.
What should he project manager have done to manage the scope change?