PMP Certification Executing Questions Test 3

© examsiri.com
Question : 67 of 70
 
Marks: +1, -0
A project manager must quickly transition another project to begin their next assignment. Several issues were scheduled to be fixed during the other project's warranty period, but stakeholders are unwilling to accept project deliverables until all issues are completed.
What should the project manager do?