A project manager is managing a project that is operating in a remote, international location. During the execution phase, a national event occurs. The project manager is concerned that the project may be negatively affected and has contacted the program manager who has agreed to provide the resources to implement a contingency plan in the event that the project is negatively affected.
What management strategy is the project manager employing?
What management strategy is the project manager employing?