PMP Certification Executing Questions Test 3
© examsiri.com
Question : 45 of 70
Marks:
+1,
-0
A project manager currently has two projects in execution. The project manager was away for two weeks of vacation, and had designated a back-up project manager for the projects. Upon returning from vacation, the project manager met with the back-up manager to discuss the projects' status and is informed about a complaint from key stakeholders following a project-status update that was sent to the team for one of the projects.
What should the project manager have done to avoid stakeholder issues while away?
What should the project manager have done to avoid stakeholder issues while away?
Go to Question: