PMP Certification Executing Questions Test 3

© examsiri.com
Question : 45 of 70
 
Marks: +1, -0
A project manager currently has two projects in execution. The project manager was away for two weeks of vacation, and had designated a back-up project manager for the projects. Upon returning from vacation, the project manager met with the back-up manager to discuss the projects' status and is informed about a complaint from key stakeholders following a project-status update that was sent to the team for one of the projects.
What should the project manager have done to avoid stakeholder issues while away?
Go to Question: