PMP Certification Executing Questions Test 3

© examsiri.com
Question : 40 of 70
 
Marks: +1, -0
During project execution, an operator identifies a requirement that was not addressed in the project management plan. The team is conflicted about whether or not this requirement should be added as a change request.
What should the project manager have done to avoid this situation?