PMP Certification Executing Questions Test 2
© examsiri.com
Question : 23 of 70
Marks:
+1,
-0
What is the estimate at completion (EAC) if the budget at completion (BAC) is 100, the actual cost (AC) is 50, and the earned value (EV) is 25?