PMP Certification Executing Questions Test 1

© examsiri.com
Question : 48 of 70
 
Marks: +1, -0
A project management team is developing a project management information system (PMIS) as a collaboration tool for internal and external stakeholders. A dashboard is updated monthly with information on the project's performance.
What type of communication method does this describe?
Go to Question: