Question : 36 of 70
Marks:
+1,
-0
During the execution of an IT project, a project manager warns of the possibility that the main server may fail due to constant, local-area electrical outages. The project manager signs a contract to rent an additional server from a local company.
What strategy is the project manager using?
What strategy is the project manager using?