PMP Certification Executing Questions Test 1

© examsiri.com
Question : 36 of 70
 
Marks: +1, -0
During the execution of an IT project, a project manager warns of the possibility that the main server may fail due to constant, local-area electrical outages. The project manager signs a contract to rent an additional server from a local company.
What strategy is the project manager using?
Go to Question: