A project has an external dependency on a changing regulatory requirement planned to go into effect after the project's scheduled go-live date. The project team informs the project manager that a missed milestone caused a delay, which could push the go-live date. This delay may result in the regulatory requirement becoming mandatory for project implementation. What should the project manager do first?