PMP Certification Executing Questions Test 1

© examsiri.com
Question : 26 of 70
 
Marks: +1, -0
The project manager for a medium-sized project expects materials from a vendor to arrive in time to deliver an upcoming milestone. However, the project manager learns there will be a three-week delay, which will directly impact the schedule. The type of contract used with the vendor was firm fixed price (FFP).
What type of contract should the project manager use in the future to mitigate vendor delays?
Go to Question: