PMP Certification Closing Test 2

© examsiri.com
Question : 23 of 45
 
Marks: +1, -0
A project manager joins an ongoing project. During a weekly status meeting, the team informs the project manager that the project plan indicates that quality assurance will be performed during the closing phase.
What should the project manager do?