Question : 65 of 70
 
Marks: +1, -0
A project team completed all development activities and delivered the product to the customer. The project manager immediately released the team to begin work on a new product. One month later, the customer complains that many functionalities fail to work as expected.
What should the project manager have done to avoid this?