PMP Certification Closing Test 1

© examsiri.com
Question : 61 of 70
 
Marks: +1, -0
A project is delivered that meets the approved business requirements. However, the client identifies a few unrelated issues that will cause a delay in final product approval and impact project closure.
What should the project manager do?
Go to Question: