Question : 23 of 70
 
Marks: +1, -0
In a housing project, the real estate developer and the building contractor disagree about the quality of the work completed by the building contractor. The real estate developer has refused to pay for the work already completed and has also asked for a discount.
How should the project manager resolve the issue?